The RA Prime Minister Nikol Pashinyan posted a video on his Facebook page from the "Let's Build Armenia in a New Way" series.
The video shows the ongoing renovation works in Armenia. The interstate road passing through the city which is 4 km long is being renovated in Spitak. Renovation began in 2019. The project is scheduled to finish for December 2020. The contract value is 504 million 999 thousand drams.
The Spitak-Mets Parni road is being repaired. The total length is 21.8 km. The contract value is 672 million drams. The renovation is scheduled for completion in December 2020.
The Vanadzor-Stepanavan road is also being renovated. The length is 2.5 km. The road has never been repaired. Construction is scheduled for completion in the summer of 2020. The contract value is 339 million 999 thousand drams.