The RA Prime Minister Nikol Pashinyan posted a video on his Facebook page from the "Let's Build Armenia in a new way" series.
The video shows the ongoing renovation works in Armenia. It is mentioned: M-14. M-4-Shorzha-Vardenis interstate highway. The length is 20 km. The works started in 2020, June. The project is scheduled to be complited in December 2020. The contract value is 1 billion 800 million drams. The last time construction work took place was in the 1990s.
Another section of the M-14. M-4-Shorzha-Vardenis interstate highway was renovated in 2019. The length is 12.5 km. The contract value is 1 billion 457 million drams.
The main road of the community, 3.3 km, is being renovated in Artsvanist. The contract value is 405 million drams. It was last renovated in the 1980s. The 22nd inter-community street is being asphalted by the subvention program. The contract value is 57 million drams.